Concrete Mix CalculatorA free tool on thebackyardscientist.com

Concrete calculator – M15, M20, M25 cement, sand and aggregate

M15 / M20 / M25 nominal mix chuniye, volume ya slab ke naap daaliye. Dry-volume factor 1.54 dikhta hai. 1 m³ M20 aur 100 sq ft × 5 inch slab ke worked examples guide mein hain.

Concrete mix calculator (M15 / M20 / M25)

Cement, sand and aggregate for one cubic metre of M20

A nominal mix such as M20 (1 : 1.5 : 3) is a site recipe, not a laboratory design mix. It still has a reliable shopping calculation. You start with the wet volume of concrete you want to place, multiply by a dry-volume factor of about 1.54 (concrete ingredients occupy more volume when they are dry and full of voids), optionally add wastage, and split the dry volume into 1 + 1.5 + 3 = 5.5 parts.

Worked example: 1 m³ of M20, 5% extra

Dry volume = 1 × 1.54 × 1.05 = 1.617 m³. Cement = 1.617 × (1/5.5) = 0.294 m³ = 0.294 ÷ 0.035 = 8.40 bags of 50 kg cement. Sand = 1.617 × (1.5/5.5) = 0.441 m³ (15.6 cubic feet). Aggregate = 1.617 × (3/5.5) = 0.882 m³ (31.1 cubic feet). Those are the numbers the default boxes are built to reproduce. M15 (1:2:4) uses less cement and more sand and aggregate; M25 (1:1:2) uses more cement.

100 sq ft slab, 5 inches thick

Switch the entry mode to “slab”. 10 ft × 10 ft × 5 inches is 100 sq ft of slab at a common house thickness: 3.048 × 3.048 × 0.127 = 1.180 m³ of wet concrete. Run that through the same M20 path and you get about 9.91 bags of cement with 5% extra, plus 0.520 m³ of sand and 1.040 m³ of aggregate. It is a much more honest 100 sq ft answer than spreading a single “8 bags per 100 sq ft” rumour that never mentioned thickness.

CaseWet volumeM20 cement, factor 1.54, 5% extra
1 m³1.000 m³8.40 bags
100 sq ft × 5 inch1.180 m³9.91 bags

Hindi mein

1 घन मीटर M20, ड्राई फैक्टर 1.54, 5% extra: लगभग 8.40 बैग सीमेंट, 0.44 घन मीटर रेत, 0.88 घन मीटर गिट्टी। 100 वर्ग फुट × 5 इंच स्लैब = 1.18 घन मीटर — लगभग 9.9 बैग। प्लास्टर वाले पेज का 1.27 फैक्टर यहाँ इस्तेमाल न करें।

What this is not

A design mix from a batching plant will change the bag count. Water-cement ratio, admixtures, pumped concrete and heavily reinforced sections are outside a 1:1.5:3 thumbnail. The dry-volume factor itself is editable if your estimating office uses 1.52 or 1.57. Do not reuse the plaster page’s 1.27 factor here — that number belongs to thin mortar, not concrete.

How to use

  1. Enter a wet volume if you already know the cubic metres, or switch to slab mode and type length, width and thickness.
  2. Pick M15, M20 or M25.
  3. Leave 1.54 and 5% unless your site instruction says otherwise.
  4. Read bags, sand and aggregate in cubic metres and cubic feet, then add the steel and shuttering estimates from the sister tools.

Nominal proportions M15 1:2:4, M20 1:1.5:3 and M25 1:1:2 are the textbook Indian site mixes (IS 456 discusses grade designations; these ratios are the usual nominal companions, not a substitute for a design mix). Dry-volume factor ~1.54 and 0.035 m³ per 50 kg bag are standard estimating constants.

Ordering sand and aggregate in cubic feet

Many Indian yards still quote sand and metal in cubic feet or in brass (100 cft). The card already prints cubic feet using 1 m³ = 35.315 cft, so you can read the number aloud to a supplier without another conversion app. For the 1 m³ M20 example, 0.441 m³ of sand is 15.6 cft and 0.882 m³ of aggregate is 31.1 cft. A 100 sq ft × 5 inch slab scales those to about 18.4 cft of sand and 36.7 cft of aggregate. If your supplier sells 20 mm and 10 mm metal as a blended “coarse aggregate”, that blend is what the third number in 1:1.5:3 is meant to represent.

Water is deliberately missing from the output. A nominal mix still needs a water-cement ratio someone on site is accountable for; printing a single litre count would pretend this page is a mix design. Add water the way your specification or batching plant requires, and do not recover a harsh mix by pouring from a hose until the slump “looks right” — that is how honeycomb and weak covers start.

Frequently asked questions

1 m³ M20 mein kitne bags?

About 8.40 bags of 50 kg cement with a 1.54 factor and 5% extra, plus 0.441 m³ sand and 0.882 m³ aggregate.

100 sq ft slab?

At 5 inches thick that is 1.180 m³, about 9.91 bags of M20 with the same factors.

1.54 kyun?

Dry ingredients plus voids occupy more volume than the finished wet concrete. Some offices use a nearby number; the box is editable.

M25 alag kaise?

The mix becomes 1:1:2, so a larger share of the dry volume is cement.

Kya yeh design mix hai?

Nahi. A plant’s design mix will differ. This is the classroom nominal mix.

Plaster wala 1.27 yahan?

No. Use 1.54-class factors for concrete and 1.27-class factors for plaster mortar.

Nominal-mix estimate only, not a design mix, slump test or structural specification.