Excavation CalculatorA free tool on thebackyardscientist.com

Excavation calculator – pit volume, bulking and tractor trips

Pit ki length, width, depth daaliye. Bank volume, bulking ke baad loose volume, aur aapki trolley ki capacity se trips nikalte hain.

Excavation volume and tractor trips

How many cubic metres will you actually cart away?

A foundation pit that measures 20 × 15 × 4 feet looks like a simple multiplication, and the bank volume — the soil still in the ground — really is that multiplication. 20 × 15 × 4 = 1,200 cubic feet, which is 1,200 × 0.028317 = 33.98 cubic metres. The complication is that once a JCB disturbs the soil it swells. That swell, called bulking, is why a pit and a tipper never seem to agree. This page applies an editable bulking percentage (default 20%) and then divides the loose volume by the capacity of the truck or tractor you type.

Worked example (the default boxes)

Bank volume = 33.98 m³. After 20% bulking the loose volume is 40.78 m³. A tractor trolley that honestly holds 2.5 m³ will need 40.78 ÷ 2.5 = 16.3 trips, which in practice means 17 trips and a driver who will tell you it was 20. Sandy soil may bulk less than 20%; recently dumped fill may bulk more. Measure the vehicle’s inner box rather than believing the painted “3 cubic metres” on the door — a heaped load is not the same as a struck load, and municipal checkpoints sometimes care.

Working space around a footing also adds volume that a neat “footing size only” calculation misses. If the drawing shows a 1.2 m wide footing but the excavator needs 300 mm on each side to place shuttering, the pit is 1.8 m wide. Type the excavated hole, not the neat concrete rectangle, or you will under-hire the tractor.

PitBank volumeLoose at 20%Trips at 2.5 m³
20 × 15 × 4 ft33.98 m³40.78 m³16.3
10 × 10 × 3 ft8.50 m³10.19 m³4.1

Hindi mein

20×15×4 फुट का गड्ढा = 33.98 घन मीटर। 20% फूलने के बाद 40.78 घन मीटर। 2.5 घन मीटर की ट्रैक्टर ट्रॉली में लगभग 17 ट्रिप। नाप उस गड्ढे की लें जो सच में खुदेगा, सिर्फ फ़ुटिंग की नहीं।

How to use

  1. Measure the hole you will actually dig, including working space.
  2. Pick feet or metres and type length, width and depth.
  3. Leave 20% bulking or change it for your soil.
  4. Type the real inner volume of the tractor or tipper.
  5. Round trips up, and keep a place to stack topsoil separately if you want it back on the garden later.

1 ft³ = 0.0283168 m³. Bulking of 10–30% is a common earthwork range depending on soil; 20% is a visible default, not a laboratory test. Vehicle capacity must be the inner box you trust, not a painted claim.

Rock excavation, dewatering and shoring are outside this tool. A deep pit next to a neighbour’s wall needs more than a volume card before anyone starts the machine.

Heaped loads and honest capacities

A tractor trolley advertised as 3 m³ is often closer to 2–2.5 m³ when you measure length × width × struck height and ignore the heap above the tailgate. Using 2.5 m³ as the default is therefore slightly conservative, which is the right direction when you are hiring by the trip. If you later measure 2.8 m³, type it. The card will drop a trip or two and you can renegotiate without guessing.

Dump the soil where it will not slump back into the pit after the first rain, and keep excavated earth at a safe distance from the edge so the wall of the pit does not collapse under the extra surcharge. Those are site-safety habits this volume card cannot watch for you.

For basement-scale holes the same formula still holds, but the logistics do not: you will need a ramp, traffic management and somewhere legal to dump hundreds of cubic metres. This page remains most useful for house footings, sumps and small swimming-pool pits where a tractor count is the question you actually have to answer this week.

Frequently asked questions

20×15×4 ft kitna volume?

About 33.98 m³ in the bank, 40.78 m³ after 20% bulking.

Bulking kya hai?

The swell when soil is dug. Default 20%, editable.

Trips kaise?

Loose volume divided by the vehicle’s inner capacity.

Working space?

Type the hole you will dig, not just the footing size.

Rock?

Not handled here.

Topsoil?

Stack it separately if you want it back — the calculator does not sort soils.

A volume sketch. It is not a method statement, shoring design or soil test.