Sand and coarse aggregate in cubic metres and cubic feet
Cement bags get most of the attention on a small Indian site, yet sand and 20 mm aggregate usually occupy more of the truck. This page converts a wet concrete volume, a plastered area, or a sand-bed thickness into cubic metres and cubic feet so you can talk to a supplier who still quotes by brass or by tractor trolley. One cubic metre is 35.3147 cubic feet.
Concrete mode — the 1 m³ M20 example
For 1 m³ of wet M20 (1:1.5:3) the parts add to 5.5. Multiplying by the 1.54 dry-volume factor and five percent wastage gives 1.617 m³ of dry material. Sand is 1.5 parts: 0.441 m³ (about 15.6 cft). Coarse aggregate is 3 parts: 0.882 m³ (about 31.1 cft). Those are the same numbers the concrete mix calculator prints, so the two pages stay consistent. M15 shifts more of the dry volume into aggregate; M25 shifts more into cement and less into both sand and stone.
Plaster sand
Switching mode sets the dry-volume box to 1.27. One hundred square feet of 12 mm plaster is 0.1115 m³ wet. In a 1:6 mix most of the dry volume is sand — the card shows that volume in m³ and cft. Cement for the same job is easier to read on the cement bags calculator or the plaster page.
Floor or filling sand
A compacted sand bed under tiles or a plinth fill is not a mortar. The dry-volume box drops to 1.00 so you are not accidentally inflating a filling quantity with a concrete factor. Thickness is in millimetres: 50 mm over 100 square feet is 0.4645 m³ before wastage, then the percentage box adds handling loss. If your specification already includes compaction allowance, set wastage closer to zero instead of stacking two safety margins.
How to use the page
- Pick the job — structural concrete, plaster, or a loose sand bed.
- Enter volume or area and thickness in the units you measured on site.
- Read both m³ and cft before you call the quarry; many yards still think in feet.
- Order a little extra only once — either in the wastage box or as an extra trolley, not both.
Moisture in river sand changes truck weight more than truck volume. This page reports volume, not tonnes. Bulk density varies with grading, so converting to kilograms here would invent a precision the pile does not have. Ask the yard for their own density if you must buy by weight.
Dry-volume 1.54 (concrete) and 1.27 (plaster mortar) match the sister tools on this site. 1 m³ = 35.3147 ft³ is the exact SI–imperial conversion (1 ft = 0.3048 m). Nominal mixes follow common Indian site practice for small residential work.
Do not mix plaster sand numbers into a concrete order without saying so — plaster sand is usually finer. Likewise, 20 mm graded aggregate for RCC is not the same as 40 mm stone for plain cement concrete in a footing. The card cannot see the sieve; it only splits parts. If the mixer operator adds extra water because the sand arrived dripping wet, the batched volume on site will drift from this estimate. Keep the first load slightly short and adjust after the pile is on the ground rather than over-ordering three trolleys “just in case” on a tight lane plot.
A brass in some markets is 100 cubic feet — divide the card’s cft figure by 100 if that is how your yard still talks. Tractor-trolley volumes vary by body size; ask the driver for an approximate cft rather than assuming every trolley equals one brass. Sea sand and crushed-stone dust are not interchangeable with river sand in reinforced concrete; the page will still print a number if you type a volume, but the specification, not the calculator, decides which pile is legal on your plot.